Thursday, January 08, 2026

Hendry County Road Work - CR78

Notice of Road Work on CR78 from Kirby Thompson Road to Hidden Hammock Drive

(January 8, 2026) – Please be advised that beginning on Monday, January 12, 2026, Hendry County’s contractor, Southern Striping Solutions, LLC, will be conducting roadway construction services on CR78 from Kirby Thompson Road to just west of Hidden Hammock Drive in LaBelle, FL.

The project includes milling and resurfacing of the existing roadway, paving of shoulders and driveway turnouts, installation of signage and pavement markings, and drainage improvements.

Visual message signs and traffic control signage will be in place to alert and guide traffic.

The speed limit will be reduced through the project area.

Motorists and pedestrians should use extra caution when traveling through the work zone.

Motorists should expect lane closures and possible delays throughout the duration of the project and allow extra time for their commute.

The project is expected to have a completion time of approximately one hundred twenty (120) days to one hundred fifty (150) days.

Roadway construction services will occur during weekdays, Monday - Friday, 7am - 5pm.

Please note that this schedule is tentative and subject to change. The Hendry County Engineering Department will notify of any changes.

Residents or motorists with any questions or concerns can contact the Hendry County Engineering Department at 863-675-5222.