Road Work Near Seminole Indian Reservation

CLEWISTON, FL. -- Hendry County will be conducting road improvements to approximately 4-miles of CR833 starting from the Big Cypress Seminole Indian Reservation working northward.

This construction project will start September 12, 2012 and is expected to last 200-days ending in March 2013. This roadway will be open to vehicular traffic, but lane closures will occur resulting in delays. Drivers should utilize caution when traveling through the construction limits and allow extra time for travel.

Road Closing On County Road 835

Hendry County is repaving approximately 3-miles of CR835 from 5.75-miles south of US27 to 2.75-miles south of US27. This construction project is expected to last 60-days ending in mid October. This roadway will be open to vehicular traffic, but lane closures will occur resulting in delays. Drivers should utilize caution when traveling through the construction limits and allow additional time for travel.

Improvements will also occur at the railroad crossings within this construction project which will require the closure of CR835 for at least one week. This 3-mile segment of CR835 will be closed starting Monday September 17, 2012 and ending Sunday night September 23, 2012. Drivers will need to seek an alternative route.

Harlem Road Closing For Gas Line

Florida City Gas is installing a gas line along Lewis Blvd from US 27 to Georgia Avenue in Clewiston. This road closure is expected to last six days from Monday, September 10, 2012 through Saturday, September 15th, 2012. Drivers should seek an alternate route during this period.
Hendry County apologizes for any inconvenience that these construction activities may cause. If anyone has any questions regarding this project they should call Hendry County Engineering at (863) 675-5222.